13.Jul.2010 Final Slab

It’s been a few weeks since the last update. Bedroom 2 has started taking shape and the walls have gone up. The last few weeks have been spent prepping the final slab for the main bedroom. The slab also forms the ceiling of the lounge & dining area. The usual steel and conduiting was laid.┬áThere […]

Comments Off on Final Slab

22.Jun.2010 Slab poured

The weather played along and after many tweaks to the steelwork, the engineer, Andy Cowie (CDA Design CC) , cast his final critical eye over everything and gave it his thumbs up – the concrete was poured onto the second floor slab. An additional beam was added above the garage and had to be poured […]